Social consequences of the Bujagali hydropower project.

August 20, 2015      

The Bujagali hydropower dam on The River Nile in Uganda was finally commissioned in August 2012 after eighteen years of controversy that delayed the dam construction.

The dam faced numerous economic, environmental, social and spiritual challenges that stalled the dam construction while the project underwent investigations over bribery claims and project reviews on the dam design and capacity.

The dam cost kept on growing from $580 million at inception to $860 million and finally $902 million ($3.6million per MW) at completion. Independent investigations by the Ugandan Parliamentary adhoc committee on energy put the dam’s actual cost at $1.3 billion ($5.2m)